PMs need to update the weekly report page by end of Friday each week. Completed milestone or updates should be kept in report for 2 weeks before removing.children



Project NameTeamStatus Updates | Expected Milestones
1

Special Tactics - Media Buyer

  • PM: An Nguyen
  • Developers: Recruiting
    • 2 night-shift developers start by 20 June
  • We have created a new request queue for Media Buyer here, taken care by An and Sida.
    • We are recruiting a dedicated team of mid-level FE devs (2 work in VN time, 2 work in Vancouver time) for this queue. 
      Status
      colourGreen
      titlein progress
  • Mindinsole - Smarthomegadget: Team completed rebuilding smarthomegadget.co to our CMS.  
    Status
    colourGreen
    titleDONE
    • Develop new presale page for split test: 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2587
        
      Status
      colourGreen
      titleIn progress
    • Change domain from /en/ to /st/: 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2764
       
      Status
      colourGreen
      titleDONE
  • Superboost - Thegadgetreviewguy: Completed building requested pages for Superboost into CMS, under testing.   
    Jira Legacy
    serverSystem JIRA
    serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
    keyDFSB-2436
    • Duplicated to AU & UK site: 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2672
       Waiting for CRM team to fix issue with Currency for user from Germany 
      Status
      colourRed
      titleON HOLD
    • Finished DE language setup: 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2615
    • On going to develop FR, DK, NO language for this site. 
  • Livewaveantenna - TVantenna Expert: Start build funnel for Germany:
    • Blog: finished rebuilding blog https://tvantennaexperts.co/ to our CMS follow Thegadgetreviewguy template
    • Funnel: start create funnel for split test  ETA  
      Status
      colourGreen
      titleDONE
2

Shopify Integration

  • PM: Khai Huynh, An Nguyen
  • Developers: Toan Nguyen, Sang Nguyen
  • QC: Nhu Phan
  • Better Back: integrated flow to redirect to Shopify checkout and 1 upsell product.
    • Waiting for BetterBack team to grant required permissions to connect our API to their store.
    • Testing payment with Paypal: need Vancouver team to help since it only can be made with Production Paypal Account 
      Status
      colourGreen
      titleIn Progress
       
    • Develop 2nd checkout solution : ETA  
      Status
      colourGreen
      titleIn Progress
  • We are creating a new Public App with Shopify Partner account to allow us to checkout using Shopify Payment API. ETA: 1 week after API request is approved 
    Status
    colourGreen
    titlein progress
    • We are submitting request to Shopify, waiting for their approval. app submission has been rejected. We are waiting for more information from Adam.
3

Funnel Building - Internal

PM: Khai Huynh

  • Hoa Xuan Tran: Lead team, handle assignment and review/publishing.
  • Developers: Phuong Tran, Chinh Phan, Yen Phan
  • QC: Nhu Phan, Kieu Nguyen
  • After the first bootcamp, we have an idea of how to improve the usability for no-code users. We are creating some use cases to try out and hopefully will be able to show in Vancouver bootcamp to get feedback.
  • InfinitiKloud is done with development, start testing on  
    Jira Legacy
    serverSystem JIRA
    serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
    keyDFSB-2566
     ETA  
  • Nutra Ketodrine funnel is completed 
    Jira Legacy
    serverSystem JIRA
    serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
    keyDFSB-2325
     
    • We're still waiting for CRM campaign information. 
      Status
      colourGreen
      titlein progress
    • eComm template for Icon Nutra designed by Sang is ready for creating products, waiting for information from CM team 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2489
       
      Status
      colourGreen
      titlein progress
  • Release all new GEOs: TR, RU. Livewave and Euphoric Feet are ready on the FE but the pricing is still pending. 
    Status
    colourRed
    titlePending
  • Coupon code API now is being put in attention of BE team and CM team. Reported issue has been fixed. Need to finalize business rules and fine tune the API. 
    Status
    colourGreen
    titlein progress
  • Testing dotCMS 5.1 upgrade. 
    Status
    colourGreen
    titlein progress
    • There are some issue with static push, Toan is testing and discuss with dotCMS team.
    • Reported performance issue.
4

Funnel Building - Client

PM: An Nguyen

  • Hoa Xuan Tran: Lead team, handle assignment and review/publishing.
  • Developers: Sang Nguyen, Tu Nguyen
  • QC: Quan Dang, Hue Tran
  • Coupon code functionality update:
    • Add function to allow user remove coupon code: 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyEC-1119
       
      Status
      colourYellow
      titleON HOLD
       → BE team need to prioritize other task 
    • Re-define & implement New Coupon code Type & Behavior: 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyEC-1120
       
      Status
      colourYellow
      titleon hold
       → BE team need to prioritize other task
  • Better Back:
    • Finished integrate shopify checkout solution for descriptive checkout 
    • Waiting for Client to give permission (Storefront access token) to Integrate Live Shop 
      Status
      colourYellow
      titleon hold
       
    • Implement Shopify checkout for Order Gentle:  
      Jira Legacy
      serverSystem JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2593
       
      Status
      colourGreen
      titledone
       waiting for client to provide Storefront access token to go live
  • New client: 
    • Caresoles: in design phase, will have campaign creation & site development next week. 
    • Frey Pre-sale: 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2738
       
      Status
      colourGreen
      titleIn Progress
       ETA  
5

Languages Site development

PM: An Nguyen

  • Thuy Tien: Coordinate with 3rd-party for translation & assign data feeding task to Data Entry team. 
  • Hoa Xuan Tran: Handle assignment
  • Dev team (support site set up & fix layout issue): Tu Nguyen, Sang Nguyen, Phuong Tran, Chinh Phan
  • QC team: Kieu Nguyen, Quan Dang, Hue Tran, Nhu Phan
  • Data Entry team
  • Data team start implement Descriptive Order & Gentle Checkout page to all Languages
  • Has been trained to duplicate content & pages for Media Buyer team.
  • Has been trained to use more efficiency tool to cross-check content.  
6

eCommerce

PM: Khai Huynh

  • Toan Nguyen: Rebuilding structure and optimization.
  • Yen Phan: FE developer
  • Nhu Phan: QC and content creation
  • Team has done updating the Navigation structure for SEO as requested, and push live   
    Jira Legacy
    serverSystem JIRA
    serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
    keyDFSB-2479
     
    Status
    colourGreen
    titleDONE
  • We have completed the SEO URL change request from Leonard, including creating 301 redirects  
    Jira Legacy
    serverSystem JIRA
    serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
    keyDFSB-2429
     
    Status
    colourGreen
    titleDONE
  • Translate dfydaily.com to DE and FR after going live. Both languages have been completed in CMS, waiting some layout fixed by developers. 
    Status
    colourGreen
    titleIn progress
  • 2 new themes are ready for creating content.
    • Leave No Print 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-1755
       
      Status
      colourGreen
      titleIn progress
        
    • Herbal products 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2489
       
      Status
      colourGreen
      titleIn progress
        
  • We are going to replicate the ecomm template to all current Cart Pages. Target to complete by end of Q2.
    • Team is rebuilding for https://www.911helpnowalarm.com/ to test with Google approval.  Moved to gethelpnowalarm.com 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2499
       
      Status
      colourGreen
      titleIn progress
    • TVSurge Cart page is also built with this new framework. 
      Status
      colourGreen
      titleDONE
  • BE has completed updating the API to reduce to 1 call. Waiting for Toan to re-test and update to live site 
    Status
    colourGreen
    titleDONE
    • We will implement the button in Product Details page for quick checkout. 
      Jira Legacy
      serverSystem JIRA
      serverIdb5f78b4b-8603-3879-a97e-a16b5dacbf76
      keyDFSB-2293
       
      Status
      colourGreen
      titlein progress
7

Fingerprint tracking

PM:

Khai Huynh

Quang Pham

  • Toan Nguyen
  • Hoa Xuan Tran
  • Nhu Phan.
  • Finger Print is live on below sites.
    • Livewave EN
    • TVradius DE
    • Superboost DE
    • TVFix EN
    • CircaCharge EN
    • Superboost EN
    • Mindinsole EN
    • CircaCharge DE
    • Euphoric DE
    • TVRadius FR
    • DFYDaily
  • Investigate on Facebook package.
8

CTRwow

PM: Quang Pham

  • BE: Tuan Pham, Huy Phan
  • FE: Tuan Phan, Hoa Thanh Tran, Giang Nguyen, Hoang Nguyen
  • QC: Hien Vo, Kim Ly
  • Tracking & Analytics implementation  
    Status
    colourGreen
    titledone
     → Demo-ed to Special Tactics team (Sebastian, Hendrik)  Planning implementation off feedbacks 
  • Next Release 3.0 to Production  
    Status
    colourGreen
    titledone
    • Tracking & Analytics
    • Enhanced builder performance
    • Bug Fixes for CRM integration
  • Enhancement Request from Demo to Bruce & Alex:
    • New samples/templates - existing templates (samples) from earlier /wiki/spaces/CTRWOW1/pages/93192225 is no longer valid, need to create new sample & template (10 versions) - CTRWOW-884  
      Status
      colourGreen
      titledone
    • Tags: Pages needs to have predefined tags so Users can select from, and then can search using the tags 
      Status
      colourGreen
      titledone
    • Funnels Configuration: select multiple landers/checkout from different sites 
      Status
      colourGreen
      titleIn Progress
    • User Journey feature/guide
  • Quick Campaign Functionality - Work BreakDown Structure (WBS)  → 
    Status
    colourYellow
    titleon hold
     discussed with Daniel, Backend API(s) need to be done first by eManage team
  • Feedback from Demo for Brennan and Adam will be planed to this Sprint 12  
    Status
    colourGreen
    titleIn Progress
9

Picksell

PM: Quang Pham

  • BE: Vy Nguyen (Hung Nguyen supports on solution and review)
  • FE: Phuong Dao
  • QC: Hien Vo
  • Release MVP Rls 1.0 to Production (PickSellPlace.com  
    Status
    colourGreen
    titledone
  • Demo-ed for CTO (Daniel), Special Tactics & San Diego team  → Alex set target to roll out the MVP for 3 commercial Sites 
    Status
    colourGreen
    titleIn Progress
  • Enhancements Implementation  
    Status
    colourGreen
    titleIn Progress
    • Dashboard - Stats for Banner
    • Ads Banner split test functionality (Product Management)
    • Ads Banner media customization (Product Management)
  • Facing issue with PayPal checkout from iFrame 
    Status
    colourGreen
    titleIn Progress
    • From Checkout page, with Credit Card or PayPal "Smart Button" payment - user can complete purchase within the iFrame and continue to UpSell purchase successfully
    • From Checkout page, with Express Paypout, PayPal security origin check block any login request NOT from PayPal → failed at login from iFrame
      • Front End team (Khai) is testing out the Smart Button implementation → need confirmation from the test
10

InfinitiKloud

PM: Binh Truong

  • TA: Hung Nguyen
  • Mobile Dev: Dang Tran, Luan Nguyen
  • QC: Kim Ly (40%)
  • Designer: Sang Le
  • Infiniti Kloud v0.2.2
    Status
    colourYellow
    titlein progress
     
    • Bug fixing
    • Prepare FAQ content
  • Infiniti Kloud Mobile v0.1: 
    Status
    colourRed
    titlein progress
     ETC: 28 Jun 2019
    • Waiting for iOS source code. iOS app is on hold.
    • Android app will still be release as plan.
  • Milestones
    • 17/6 Finish testing Android app
    • 28/6 Android app final version is ready
11

Health Check

PM: Binh Truong

  • Auto: Trung Nguyen, Duong Trinh, Hanh Pham
  • Prepare How-to video.
  • Analysis sales funnel of CTRWow
12

OBD2 Automotive Diagnostic Scanner 

PM: Binh Truong

  • R&D: Hung Nguyen

Status: 

Status
colourYellow
titledocumentation

Implement PoC to communicate with ODB II.

Issue: Binh & Hung don't have knowledge on this area. Documents and information is scarce. The progress is slow.

  • Binh provides the supplier the features & functions that we intent to have.
  • Remy will follow up with the supplier to ensure they can provide the OBD with above features & functions.
  • Binh is creating wireframes.
13

Smart scale

PM: Binh Truong

  • R&D: Hung Nguyen

Hung knows how to use Yolanda scale with app on Android.

Hung is focusing on OBD4U project

Status: 

Status
colourYellow
titleon hold